Connectivity Enhancement Project
- Project typeUpgrade works
- Forecast completionTBA
Project status as at
31 March 2025
- BudgetOn budget
- ScheduleOn schedule
- ScopeAgreed scope
- Project updateComponent 1 (Kerb & Channel at Adams Street, Stradbroke Avenue, Footpath at Coronation Avenue): Works Complete. Defects rectified.
Component 2 and 3 (footpaths at Manangatang, Ultima, Woorinen South):
Footpath works complete at Ultima.
Works for Woorinen South & Manangatang to be re-tendered.
Kerb and Channel, Footpath construction works across multiple locations in the municipality.
- Component 1
Kerb and Channel at Adams Street, Stradbroke Avenue, Footpath at Coronation Avenue
- Component 2 and 3
Footpaths at Manangatang, Ultima, Woorinen South
Any dates provide are subject to contract agreement, weather conditions and any other unforeseen delays.