Lake Boga Southern Entrance Beautification
- Project typeBeautification
- Contractor nameThink Water
- Forecast completionMay 2025
Project status as at
31 March 2025
- BudgetOn budget
- ScheduleBehind schedule
- ScopeAgreed scope
- Project updateIrrigation system operational. Tree planting and pump connection planned after Easter.
This project aims at enhancing the view of the Southern entrance of the Lake Boga.
The project comprises a new pump, pump shed, new irrigation system to Southern precinct, bollard treatment and cable to the West side of walking path, and tree planting.
The design and construct project was awarded to Think Water.
Any dates provide are subject to contract agreement, weather conditions and any other unforeseen delays.
Location
Murray Valley Highway, Lake Boga 3584 View Map
-35.46677998458417, 143.64833260549094
Murray Valley Highway ,
Lake Boga 3584
Murray Valley Highway ,
Lake Boga 3584
Lake Boga Southern Entrance Beautification