Robinvale Key Workers Accommodation
- Project typeBuilding Construction
- Contractor nameGJB Building Group Pty Ltd, Eco Infrastructure
- Forecast completionJune 2026
Project status as at
30 September 2025
- BudgetOn budget
- ScheduleOn schedule
- ScopeAgreed scope
- Project updateAs of mid-June 2025, the project commenced on site with the civil works. These works include new retaining wall, fencing, demolition of existing road infrastructure, installation of sewage for the new units, stormwater network, and the construction of access road for the new units. Building permits issued late August, the foundations commenced soon there
after and were completed by the end of September.
Framing works started in late September, anticipated to be complete in October 2025. Lock up works, windows, external cladding will be ongoig through the remainder of 2025.
This exciting project will transform an underused site in Robinvale into a vibrant new neighbourhood designed to support key workers. It will feature a mix of modern, affordable homes for individuals, families, and shared living—helping attract and retain the skilled professionals who are vital to the town’s future.
Any dates provide are subject to contract agreement, weather conditions and any other unforeseen delays.