Connectivity Enhancement Project
- Project typeUpgrade works
- Forecast completionTBA
Project status as at
30 September 2025
- BudgetOn budget
- ScheduleOn schedule
- ScopeAgreed scope
- Project updateComponent 1 (Kerb & Channel at Adams Street, Stradbroke Avenue, Footpath at Coronation Avenue): Works Complete. Defects rectified.
Component 2 and 3 (footpaths at Manangatang, Ultima, Woorinen South) No site works yet for Woorinen, Manangatang works completed with PC issued,
defect to be rectified by end on Nov’25, Ultima completed, no defects.
Kerb and Channel, Footpath construction works across multiple locations in the municipality.
- Component 1
Kerb and Channel at Adams Street, Stradbroke Avenue, Footpath at Coronation Avenue
- Component 2 and 3
Footpaths at Manangatang, Ultima, Woorinen South
Any dates provide are subject to contract agreement, weather conditions and any other unforeseen delays.