Little Beveridge Street Reconstruction

  • Project typeRoad Rehabilitation
  • Contractor nameWhitfield Excavations Pty Ltd
  • Forecast completionMarch 2026

Project status as at 31 March 2026

  • BudgetOn budget
  • ScheduleBehind schedule
  • ScopeScope increase
  • Project updateWorks completed in accordance with tender design. Tree root barriers approved as a contract variation and scheduled for installation in May.
Any dates provide are subject to contract agreement, weather conditions and any other unforeseen delays.