Request an extension of time to a building permit

When you are issued a building permit, the permit includes:

  • the date when the work must commence, and
  • the date when work must be completed

If you are unable start or finish the works within the time on your permit, you must apply for an extension before the date expires. 

You may also receive a letter from Council advising your permit is due to expire.  If so, you need to apply to extend your permit or let us know if you no longer require the permit.

Types of extensions available

  • First request - additional 12 months extension provided
  • Second request - additional 6 months extension provided
  • Third and final request - additional 3 months extension provided

Council will not grant any further extensions and your current building permit will lapse. You will then need to apply for a new Building Permit.

How to apply

Online

Step 1.Have the details ready

You will need to provide:

  • the building permit number
  • the property details
  • describes the stage of work
  • describe the work to be completed 
  • information about why you are requesting an extension of time

Step 2.Submit the online form

Request an extension of time - Building Permit

Fees

Extend a building permit 2026/27 Fees
Domestic $245.50
Commercial $523.00