Request an extension of time to a planning permit

As the owner or occupier of the land, you may apply for an extension of time to the commencement or completion date of an existing permit:

  • Within 6 months after the permit expiry date, where the use or development allowed by the permit has not yet started (commencement); or
  • within 12 months after the permit expiry date, where the development allowed by the permit lawfully started before the permit expired, but has not been completed

A permit cannot be extended if a request is made outside the above timeframes and you will not be able to apply to VCAT for a review of the matter. You will need to apply for a brand new planning permit.

It is up to Council as to how long your planning permit is extended. Council might also decide on a different date for your permit extension, rather than what you have requested.

The following circumstances have a strong impact on whether Council approves the request (and for how long):

  • Whether there has been a change of planning policy
  • Whether the landowner is seeking to “warehouse” the permit
  • Intervening circumstances as bearing upon grant or refusal
  • The total elapse of time
  • Whether the limit originally imposed was adequate
  • The economic burden imposed on the landowner by the permit
  • The probability of a permit issuing should a fresh application be made

How to apply

Apply online

Step 1.Prepare your supporting documents

You will be required to provide the following information:

  • Proposed timeframes for commencement and completion
  • A description of the reasons you are requesting the extension
  • Proof that the development has commenced before the expiry date

Step 2.Have your credit card ready

Please note we only accept Visa or MasterCard.

Step 3.If you were the original applicant

Step 4.If you were not the original applicant, or the permit was issued before 2021

Fees

Extension of time to Planning Permit 2026/27
1st Request $290.00
2nd Request $580.00
3rd Request $750.00

If you are unsure on how many times the permit has been extended, please email planning@swanhill.vic.gov.au and a member of our Planning Team will be in contact with the details.

What happens next?

After your request to extend has been submitted and the fee paid, a member of the Planning Services team will assess the request and provide a written response.

If your request is refused and it was lodged within the relevant statutory timeframe, you may apply to the Victorian Civil and Administrative Tribunal (VCAT) to have the decision reviewed.